ROBAR Civil have completed the last structural pour on the Carmichael Rail Network project. It is now time to pack up and head towards new challenges.
ROBAR Civil has placed 1,160m3 of concrete, installed 250 tons of steel and form 3,200m2 of structures. We completed three bridges and three culverts. The ROBAR Team has completed all contract works and demobilisation from site. A challenging project overall. However, ROBAR met the clients program requirements upon access being provided by the client. Project Scope included: – 3No. Conventional in-situ Culverts and – 3No. Bridges; Abutments, Piers [2, 3 and 4 piers] Headstocks, Restraints ROBAR Team completed with zero medical or lost time injuries.